Of the three key variables in quantum risk, migration duration is the one an organisation most needs to work out for itself — and the one most consistently underestimated. This article covers bottom-up estimation, reference-class forecasting and pilot calibration, and why dependency waits always get left out.

Published 22 November 2026 · 5 min read · PQ Frontier

Estimating Migration Duration: Why Every Organisation Underestimates the Y
AI-generated site artwork
Video explainer · Risk Assessment Models: from signed evidence to ranked risk

Data shelf life is written in the organisation’s own classification policy, and the threat timeline can be borrowed from experts — but migration duration, the number of years from starting today to switching the last system over, must be estimated by the organisation itself, and the cost of getting it wrong is the most direct: it determines whether you are already late. Unfortunately, this variable is also the most systematically underestimated, and in a remarkably consistent way.

Where the Underestimation Happens

Post-mortems of completed large-scale cryptographic migrations (previous hash-algorithm and key-length upgrades, for instance) show that overruns rarely come from coding and testing themselves. They concentrate in four kinds of waiting. First, vendor waiting: commercial software and cloud services embedded in your systems will release their post-quantum versions on their schedule, not yours, and your migration must wait for them. Second, standards and compliance waiting: some sectors cannot move until regulatory details or certification schemes land, and that wait is measured in years. Third, hardware-cycle waiting: HSMs, smartcards and embedded devices can only migrate with their refresh cycles, which may run five to ten years. Fourth, window waiting: core systems can only switch during annual maintenance windows or business low seasons — miss a window and you wait another year.

These four waits share one property: none of them appears in an engineering team’s effort spreadsheet. Estimating from effort yields “pure construction time”; the real calendar duration is construction and waiting interleaved. The underestimation is not carelessness — it is estimating the wrong object: workload instead of calendar.

Three Methods, Triangulated

Bottom-up estimation. Start from the cryptographic asset inventory and estimate system by system: how long for inventory confirmation, design, development, testing and cutover — then annotate each system with its external dependencies (vendor versions, hardware cycles, cutover windows) and add the waiting explicitly into that system’s calendar duration. Aggregate not by summing all systems, but by finding the critical path: the longest chain under parallel execution. Bottom-up estimation is detailed and locates bottlenecks; its weakness is optimism at every step, which the other two methods exist to correct.

Reference-class forecasting. Do not look at your own plan; look at peers’ outcomes: how many years did comparable organisations actually take for similar migrations? The reference class naturally includes all waiting and surprises, making it an external corrective to internal optimism. Comparability matters: if system counts, regulatory environments or outsourcing ratios differ greatly, adjust the reference before using it — and prefer the slower reference when in doubt.

Pilot calibration. Migrate one or two medium-complexity systems end to end first, measure the actual time per phase including waits, and correct the full estimate with the measured rates. Pilots have a valuable by-product: they expose hidden dependencies the inventory missed — an ageing component, a certificate chain nobody remembers — and those discoveries often correct the estimate more than the rates themselves.

Why Adding People Does Not Compress the Calendar

When an estimate comes in too long, management’s first instinct is to add people and budget, as if total duration were inversely proportional to resources. That holds partially for pure construction, but usually fails for the migration as a whole — again because of waiting. A vendor’s release will not arrive earlier because you hired more staff; a hardware refresh cycle will not shorten because the budget doubled; the annual cutover window will not open twice a year. Resources can compress only the internal phases — design, development, testing — which typically account for a third to a half of total calendar time.

The levers that genuinely compress total duration are different. First, start the waits early: during the inventory phase, confirm roadmaps with key vendors and write them into contract terms, so the vendor’s clock starts ticking in sync with yours instead of your discovering mid-build that they have not scheduled anything. Second, use the waiting time: while a vendor version is pending, complete the internal work that does not depend on it — interface abstraction, the algorithm-agility layer, certificate management processes — so that when the version lands, only the switch remains. Third, negotiate window flexibility: agree fallback windows or phased cutover arrangements with the business in advance, so missing the main window does not cost a full year. None of these costs much money, yet all act directly on the component that determines total duration — and an estimate whose assumptions state whether they are in place is an estimate with management meaning.

Output Form: Ranges, Phases and a Wait List

The estimate should not be delivered as a single number. Three artefacts are more useful. First, phased duration ranges: inventory, pilot, rollout and tail phases each get a range whose width honestly reflects that phase’s uncertainty. Second, a wait list: every system’s external dependencies, expected readiness dates and owners in one table — the object tracked year by year, so each vendor slip updates the list and shifts the total. Third, a critical-path statement: which few systems set the floor on total duration. If management wants to compress the timeline, only those systems matter; adding people elsewhere achieves nothing.

Finally, establish a re-estimation rhythm. Migration duration is not estimated once and frozen. Re-estimate annually against pilot measurements, vendor progress and inventory changes, and log the variance between estimate and actual. That variance log is the calibration data for the organisation’s estimating ability — the next migration will be estimated better because of it.

Conclusion

The enemy of migration duration estimation is not technical difficulty; it is mistaking a calendar problem for an effort problem. Make waiting explicit, hold down optimism with the reference class, anchor the estimate in pilot measurements, and re-estimate on a rolling annual basis — with those four practices, the chronically underestimated Y becomes the most trustworthy input in the risk model.

Tags: migration planningeffort estimationproject managementrisk assessment