The Input Variables of Threat Modelling: The Table an Organisation Can Actually Fill In
Quantum threat modelling does not require predicting the future; it requires filling in the variables an organisation can determine for itself first: data confidentiality lifetimes, system migration lead times, the distribution and dependencies of cryptographic assets, exposure surfaces and compliance deadlines. This article takes the input table apart item by item, explaining how to set each value and where a wrong entry leads the conclusion astray.
When quantum threat modelling is discussed, attention is usually drawn to the single most uncertain variable — when the CRQC arrives. But the actual structure of the modelling is the opposite: in the Mosca inequality X+Y>Z, Z is only one of three variables, and the only one that needs outside help. X (the confidentiality lifetime of the data) and Y (the time needed to complete migration) are determined entirely by the organisation’s own business and systems; together with asset distribution, exposure surfaces and external deadlines, they form an input table the organisation is fully capable of filling in itself. This article takes that table apart item by item: what each item is, how to set its value, and where a wrong entry leads the conclusion astray.
Variable one: confidentiality lifetime X — set by sensitivity lifespan, not system lifespan
The confidentiality lifetime asks: starting today, for how many years must a piece of data remain secret before it loses its value? Its most common error is substituting the system’s replacement cycle — a system retiring in five years does not mean data sent five years ago may become public in five years. Correct valuation requires inventorying data class by class:
- Long-lived data, measured in decades: medical records, genomic data, state secrets and diplomatic archives, long-term commercial contracts and M&A files, life-insurance and pension data — the X of such data is commonly in the 10–30 year range.
- Medium-lived data, measured in years: pre-publication financial reports, product roadmaps, litigation material, unreleased earnings — X in the 1–5 year range.
- Short-lived data: session content, one-time codes, short-term operational data — X measured in days or months, and quantum risk is essentially irrelevant to it.
Underestimating X has systematic consequences: the left side of the inequality is computed too small, the conclusion slides toward “there is still time”, while the real exposure began the moment the data was recorded. The conservative principle is: when unsure, take the longer confidentiality lifetime, because the cost of overestimating X is merely starting migration earlier, while the cost of underestimating it is data expiring in an irreversible state.
Variable two: migration lead time Y — set by end-to-end actuals, not planned durations
The migration lead time asks: from the decision to start until the last dependency is replaced, how long does it take? The schedule shows the duration of the algorithm swap, but in the real world the bulk of Y lies elsewhere:
- Inventory time: finding every cryptographic dependency — including those hidden in libraries, firmware, vendor products and legacy protocols — is often the least compressible segment of the whole cycle.
- Vendor dependencies: if a critical system depends on an external vendor’s post-quantum roadmap, the organisation’s Y is hostage to the vendor’s Y; this part must be listed separately and marked uncontrollable.
- Interoperability and regression testing: transitional forms such as hybrid key exchange and dual signatures must be validated against every peer one by one, and the test matrix grows quadratically with the number of peers.
- Freeze windows and change cadence: financial, medical and industrial systems have strict change windows, so calendar time runs far longer than engineering time.
On method: an honest Y should reference the organisation’s own historical actuals for comparable migrations (hash algorithm transitions, TLS version upgrades), not the project plan. Typing the planned duration straight into the inequality is the most common self-deception in modelling.
Variable three: asset distribution and exposure — deciding which objects the inequality applies to
X and Y are not two organisation-wide numbers; they differ asset by asset. The third input to the model is an asset table: each system’s data class (which sets its X), its cryptographic dependency list (which sets its Y), and its exposure properties (which decide whether it bears harvest-now-decrypt-later risk). The most critical exposure property is recordability of traffic: encrypted traffic crossing the public Internet, wireless links or any untrusted channel should be assumed recorded or recordable by default, with the confidentiality clock starting at the moment of recording; static data inside a closed network, by contrast, has a risk shape that depends on the copyability of its storage medium. Without this asset table, the inequality yields only a coarse organisation-wide average judgement, not an actionable priority order.
Variable four: external deadlines — hard constraints from compliance and contracts
The last input comes from outside the organisation: regulatory timetables (such as NIST’s deprecation and disallowance milestones for traditional public-key algorithms, and migration guidance for critical-infrastructure sectors in various countries), contractual requirements from customers and partners, and compatibility milestones up and down the supply chain. These deadlines do not change the physical risk, but they change the decision’s due date: even where the risk calculation says there is time, a compliance deadline effectively compresses the Y of certain systems. Listed as their own column, they turn the model’s output from an abstract risk score into an action table with dates on it.
A further caution: the variables are not independent
Finally, note that the variables on the table are not independent of one another, and two couplings deserve attention when setting values. First, X and Y interact: once migration starts, newly generated data immediately gains post-quantum protection, but the coexistence window in which old and new systems run side by side creates new exposure surfaces of its own — the longer the window, the larger this incremental exposure — which in turn constrains Y with a “cannot be stretched indefinitely” condition. Second, the asset table updates itself in the course of modelling: the inventory itself discovers dependencies nobody knew about, so the first Y filled in is almost always too small; the disciplined practice is to make inventory a rolling, standing activity rather than a one-off sprint before the migration project begins. Acknowledging the couplings and reserving a rhythm for revision is what makes the input table a living table rather than a one-time compliance document.
Conclusion: pin down the variables you control first
The correct posture for threat modelling is to isolate the uncertainty into the smallest possible block: X, Y, the asset table and external deadlines are all determined by the organisation’s own facts. Fill them in solidly, item by item, and the only remaining unknown is Z alone. At that point, whichever quantile of the expert distribution Z is taken from, the robustness of the conclusion is far higher than that of a discussion starting from an empty table. In other words, 90% of the work of quantum threat modelling is not predicting the future but inventorying the present — and that is its fundamental difference from fortune-telling.
Tags: threat modellingMosca inequalitycryptographic asset inventorymigration lead time